Which part of the project charter addresses project limitations?

  1. Milestones

  2. Constraints

  3. Assumptions

  4. Risks

The correct answer is: Constraints

The correct answer is identified as constraints, as this section of the project charter specifically outlines the limitations and restrictions that may impact the project's execution. Constraints typically include factors such as budget limits, resource availability, time restrictions, and regulatory requirements that need to be adhered to. Understanding these constraints is crucial for effective project planning and execution, as they establish the boundaries within which the project must operate. In contrast, milestones refer to significant events or achievements within the project's timeline, serving as markers for measuring progress rather than limitations. Assumptions list the conditions that are believed to be true for the project but are not verified, while risks focus on potential negative events or uncertainties that could impact the project's success, without necessarily detailing the restrictions or limitations imposed on the project. Thus, constraints provide a clear view of what the project must navigate, clarifying any limitations that may affect its successful completion.